 -2024 -

 January - June - Fire Suppression System Installation

July - September -  Interior Electrical, & Plumbing Completion

October - December - Insulation, Drywall, & Flooring


 -2023 -

July- Cement Pour, Interior Framing, & HVAC

April - June - Siding, Kitchen Equipment Installation, & HVAC

March - Windows & Interior Framing

January - February - Trusses & Roof Sheeting (Continued)

February - March - Frame Trusses That Connect To Original Roof Line | Begin Plumbing

April - May - Siding


 -2022 -

Spring - Summer - Foundation Work & Framing

Fall - Framing

December - Trusses & Roof Sheeting

 -2021 -

May 5th - Excavation Preps for Soldier Pile Wall Begin

May 13th - Soldier Pile Wall Machine Delivery

May 17 - Soldier Pile Wall Construction Begin

June 2 - Soldier Pile Wall Construction Complete

June  - July - Finish Foundation Dig Out

July - August - Begin Foundation Construction (lasts 5 weeks)

September - October -Foundation Cement Work