EXPANSION TIMELINE

GATEWAY'S 2021 BUILDING PROJECT

Our Foundation Permit was issued on April 13, 2021, and we are now ready to start work on the foundation of our expansion project! The rest of the building permits will come soon. Once we have final permits in-hand, we anticipate the expansion project taking about a year to complete. That means we are hypothetically looking at a completion date in mid-to-late 2022.

May 5th - Excavation Preps for Soldier Pile Wall Begin

May 13th - Soldier Pile Wall Machine Delivery

May 17 - Soldier Pile Wall Construction Begin

June 2 - Soldier Pile Wall Construction Complete

Week of June 7th - Finish Foundation Digout

June 14th - Begin Foundation Construction (lasts 5 weeks)

July 19th - Stormwater Piping Installation (3 weeks)

August 9th - Plumbing, Groundwork for Inside.

September - October - Framing

Late October - November - Roof trusses, sheeting, roofing