-2024 -
January - June - Fire Suppression System Installation
July - September - Interior Electrical, & Plumbing Completion
October - December - Insulation, Drywall, & Flooring
-2023 -
July- Cement Pour, Interior Framing, & HVAC
April - June - Siding, Kitchen Equipment Installation, & HVAC
March - Windows & Interior Framing
January - February - Trusses & Roof Sheeting (Continued)
February - March - Frame Trusses That Connect To Original Roof Line | Begin Plumbing
April - May - Siding